House log - 03/11/21

November 3rd, 2021 - House(1 min)

Today is the day where the electricity distributor comes in. In the morning I confirmed (again) they would arrive.

… And so they did, almost one hour earlier than they said :)

They did great work and now all electricity works are done! Woo-hoo!

We installed the big window and figured out that we need a top light because the strip won’t provide too much light.

State of the house

The house state today is:

  • Paint
  • Parquet
  • Tiles
  • Security
  • Doors (70%)
    • Ordered entrance door
    • Install entrance door
    • Ordered interior doors (5)
    • Order rest of the doors
    • Install the 5 doors
    • Install the rest of the doors
    • Ordered glass for the railings
    • Install glass for railings
    • Ordered replacement for broken window
    • Install replacement broken window
  • Carpentry
    • First flight of stairs
    • Second flight of stairs
    • Black finishes walls
    • Black finishes windows
    • Vinyl parquet basement
  • Plumbing (70%)
    • Install plumbing
    • Install floor heating
    • Install the heat pump elements
    • Connect the interior/exterior heatpump elements
    • Perform final checkup of the heat pump
    • Perform mise en route (aka start + warranty)
    • Integration with KNX
    • Install bathtub
    • Install sinks upstairs
    • Install sink downstairs
    • Shower panels downstairs
    • Shower panel upstairs
  • Ventilation (70%)
    • Install ventilation pipes
    • Install ventilation machine Zehnder 350Q
    • Intake, exhaust filters
    • Optional increase the capacity of the ventilation system (PEB)
  • Electricity (50%)
    • Cables are laid
    • High power electrical panel connections
    • KNX panel modules for lights installed
    • KNX panel modules for heating installed
    • KNX line couplers and interface installed
    • KNX wall bus couplers (200800)
    • KNX switches (including frames)
    • Test lights
    • KNX programmed
    • Lights - about 50% of them are done.
    • Meter moved inside
      • Application
      • Quote
      • Scheduled date
      • Execution
  • IT
    • WiFi Installation
    • Cables from the panel to IT room
    • Second rack (50%)
      • Buy
      • Install
    • Infra installation
    • Network config
    • Domain config
    • Website config
    • HA config
  • Final operations (25%)
    • Clean the house
    • Clean the outside
    • Pathway
    • Driveway
  • Finishes
    • Install big mirror
    • Install the swivel cabinet
    • Soap holder ground floor
    • Soap holder first floor
    • Cabinet between the sinks first floor
    • Storage cabinet first floor