Today I went to the house with two items in mind:
- Wait for the guy with the digger to get the driveway started and
- Be present when the electrical distributor would come to move the meter inside the house.
Digging
The guy was supposed to come at 07:30 in the morning, but at 07:00 I got a call that he was already there. So I had to rush to get there and call our guy to let him know. So at 07:30 the work started and it was finished in about two hours. Cool! We both thought it’d take longer.
Electricity
The distributor was supposed to come between 13:30 and 15:30. Unfortunately, around 15:30 I got a phone call that they were at the corner of the road. When I went there, I couldn’t see anyone and a bit later I got another phone call saying that the workers left and they would come ‘tomorrow’. Enter panic mode.
I called the distributor and confirmed (sort of) verbally they would indeed come the next day. As we did not get a confirmation, we were still a bit stressed.
State of the house
The house state today is:
- Paint
- Parquet
- Tiles
- Security
- Doors (60%)
- Ordered entrance door
- Install entrance door
- Ordered interior doors (5)
- Order rest of the doors
- Install the 5 doors
- Install the rest of the doors
- Ordered glass for the railings
- Install glass for railings
- Ordered replacement for broken window
- Install replacement broken window
- Carpentry
- First flight of stairs
- Second flight of stairs
- Black finishes walls
- Black finishes windows
- Plumbing (70%)
- Install plumbing
- Install floor heating
- Install the heat pump elements
- Connect the interior/exterior heatpump elements
- Perform final checkup of the heat pump
- Perform mise en route (aka start + warranty)
- Integration with KNX
- Install bathroom
- Install sinks upstairs
- Install sink downstairs
- Shower panels downstairs
- Shower panel upstairs
- Ventilation (70%)
- Install ventilation pipes
- Install ventilation machine Zehnder 350Q
- Intake, exhaust filters
- Optional increase the capacity of the ventilation system (PEB)
- Electricity (50%)
- Cables are laid
- High power electrical panel connections
- KNX panel modules for lights installed
- KNX panel modules for heating installed
- KNX line couplers and interface installed
- KNX wall bus couplers (200800)
- KNX switches (including frames)
- Test lights
- KNX programmed
- Lights - about 50% of them are done.
- Meter moved inside (75%)
- Application
- Quote
- Scheduled date
- Execution
- IT
- WiFi Installation
- Cables from the panel to IT room
- Second rack
- Infra installation
- Network config
- Domain config
- Website config
- HA config
- Final operations (25%)
- Clean the house
- Clean the outside
- Pathway
- Driveway