House log - Electricians and Kitchen

July 14, 2020Category: House
Today I went to the house in the morning to meet with the kitchen builders for the final measurements and with the electricians. Kitchen I've met the owner of the company, Mr. Thonon who's a very nice guy. They basically tole me that they don't need me while they take measurements. They told me at…

House log - New meeting with DaVinci

June 30, 2020Category: House
Today we met with the site engineer again. It looks like, following our/electricians' complaints, the translator is no longer involved. We exposed our points to the site engineer. He made notes throughout the meeting. He told us that electricians should start soon and finish in 2 weeks. Once that's…

House log - Sewage

June 13, 2020Category: House
Today I met with the sewage engineer. We had a short discussion where we agreed where the entry point and depth for the sewage will be. Everything will be in a corner, at -1.5m depth. The work will take approx one month and wil cost 2000-ish Euro (as per the Commune tariffs). I have to say the…

House log - Progress 05/28

May 28, 2020Category: House
Today was a second eventful day. We had a meeting scheduled from 10:30, with three points: Finalise discussion with the electricians Decide on the sewage (-3m + pump or -.7m gravitational) Visit from a prospective client When I arrived at the site, I've been told by the translator that the…

House log - Progress 05/27

May 27, 2020Category: House
Today was an eventful day. I first went to the house to let the guys who built the cellar to come and get their metal posts. This came as a surprise and took a bit of time. I then met with the electricians at COB, because they insisted they could not talk to the constructor anymore. At the…

House log - Progress 05/24

May 24, 2020Category: House
Today we went to the house to look at the electrical stuff (positions) and see if we need anything else. We ended up staying a couple of hours discussing about it and came up with a bunch of changes. The text below will be in French, because it's a message we sent to the electricians and the…

House log - Progress 03/04

March 4, 2020Category: House
Today I went to see the progress on the site. The electricians got the plans and are doing the grounding of the house and The civil engineering company will put stones around (we went for recycled stones). Stones and earth There's still a bit to be done in the back: TODO The electricians did the…

House log - Progress 03/03

March 3, 2020Category: House
This morning I had a meeting with the civil engineering company and electricians: The electricians got the plans and are doing the grounding of the house and The civil engineering company will put stones around (we went for recycled stones). Wrap and grounding HTH,

House log - Progress 29/02

February 29, 2020Category: House
Today I drove down to the building site to see if there was any progress. I took note of the two pipe holes for the heat pump: Heat pump

House log - Progress 27/02

February 27, 2020Category: House
Today I drove down to the building site to see if there was any progress. Honestly, I did not expect too much to happen, since here is snowing. Well, surprise: Cellar Fab! ..but now the first bill will come also...